RIC 2022 TH25 Practical Experience in Executing a 10 CFR Part 52 Combined License for Vogtle

TH25 Practical Experience in Executing a 10 CFR Part 52 Combined License for Vogtle Units 3 and 4
This session will discuss the lessons learned in completing a combined license under 10 CFR Part 52, “Licenses, Certifications, and Approvals for Nuclear Power Plants,” for the Vogtle Electric Generating Plant, Units 3 and 4, concentrating on the completion of inspections, tests, analyses, and acceptance criteria; significant license amendments; construction inspection; and any lessons learned that can also be applied to construction of future plants under 10 CFR Part 53 “Licensing and Regulation of Advanced Nuclear Reactors.”

Source: https://ric.nrc.gov/docs/abstracts/sessionabstract-29.html

SESSION CHAIR(S):
Omar Lopez-Santiago, Deputy Director, Division of Construction Oversight, RII/NRC e-mail: [email protected]

SPEAKER(S):

Introductory Remarks
Omar Lopez-Santiago, Deputy Director, Division of Construction Oversight, RII/NRC
Zach Harper, Manager, Plant Licensing Engineering, Westinghouse Electric Company, LLC
Amy Chamberlain, Nuclear Development Regulatory Affairs, Southern Nuclear Operating Company
Nicole Coovert, Chief, Construction Inspection Branch I, Division of Construction Oversight, RII/NRC
Victor Hall, Chief, Vogtle Licensing & ITAAC Branch, Vogtle Project Office, NRR/NRC

SESSION COORDINATOR(S):
James Gaslevic, Reactor Operations Engineer, Vogtle Licensing and ITAAC Branch, Vogtle Project Office, NRR/NRC e-mail: [email protected]